How to write a manufacturing RFQ for a Turkish factory
A useful manufacturing RFQ does more than ask a factory for a unit price. It tells every recipient which part to quote, what may change, and how the response should separate recurring costs from one-off work. If you already have factory contacts in Turkey, the immediate problem is not finding more names. It is getting quotations based on the same instructions. This guide builds one reusable request around a machined industrial spacer rather than a garment or consumer product.
ArdimexPublished Updated 4 min read

Start with one controlled drawing revision
Give the component a consistent part reference and identify the drawing revision in both the email and the attachment name. For example, an illustrative request for a stainless-steel spacer could refer to drawing SPACER-A, revision C. A factory quoting an earlier drawing is not responding to the same requirement, even if the part description sounds unchanged.
Attach the drawing and any available model, but state which document controls if the two disagree. If an old sketch contains unapproved dimensions, remove it from the package rather than expecting the recipient to work out which version is current.
As a U.S. illustration of the information used to describe manufacturing requirements, the NIST Supplier Scouting Playbook includes fields for dimensions, tolerances, materials, performance needs and business inputs. It is a reference for describing inputs, not a Turkish quotation rule.
Specify tolerances where they change the work
A dimension without a tolerance leaves room for different interpretations. Mark critical hole sizes, concentricity, surface finish and any fit that affects the assembly. Separate those requirements from ordinary dimensions; applying unusually tight limits to every feature can prompt a factory to quote a more demanding process than the part actually needs.
Say whether the material grade is fixed and whether finishing is required. For the spacer, the bore may control its fit while an outside edge needs only deburring. If the drawing contains a general tolerance note, identify it clearly and call out exceptions. Include the requested inspection evidence as part of the technical response, such as dimensional results for the features that govern assembly.
Make assumptions and alternatives visible
In a manufacturing RFQ, ask each recipient to state every assumption that could change the result. Common examples are using bar stock rather than a near-net blank, quoting a different material grade, treating a finish as optional, or assuming a batch size that was not requested. Hidden assumptions make quotations hard to compare.
Offer a simple rule: quote the specified design as the base case, then place any proposed alternative in a separate line with its technical difference explained. Do not allow an alternative to silently replace the requested part. Record unanswered questions before interpreting a quotation as complete. For an unworkable feature, ask what change is proposed before revising your drawing.
Ask for a price breakdown and quote conditions
Request a unit quotation for each stated quantity band and a separate entry for any tooling, fixtures, programming or setup charged outside the unit rate. Ask whether a one-off charge repeats on a later order and whether the quoted unit rate assumes that tooling already exists. A low recurring unit figure and a separate setup charge are not directly comparable with an all-inclusive unit figure.
Also request the quotation currency, production lead time, minimum production quantity, packaging assumption, validity period and the point at which the quoted scope ends. This article deliberately stops at the factory quotation; if your separate question is the total cost after movement and import, see the import cost guide.
Use this manufacturing RFQ email
Before sending this manufacturing RFQ, replace the illustrative part reference, drawing revision and production details with your approved information.
Subject: Manufacturing RFQ for machined stainless-steel spacer, revision C
Hello production team,
Please quote the attached industrial spacer using the controlled drawing revision C.
- Base specification: Quote the drawing as supplied, including material grade, critical bore tolerance, surface finish and deburring notes.
- Volume: Show the unit rate separately for our pilot batch and the recurring batch described in the attached requirement sheet.
- Nonrecurring work: Itemize tooling, special fixtures, programming and setup outside the unit rate, or say explicitly that none is separately charged.
- Assumptions: State any exclusions, drawing conflicts or process assumptions. Present technical alternatives as separate options.
- Conditions: State production lead time, minimum production quantity, quotation validity, packing basis and the currency used.
Please identify the drawing revision on your quotation and send questions before finalizing any assumption that changes the specification. Thank you.
Compare the same component across two offers
Hypothetical comparison: Factory A quotes the specified spacer with a single unit rate and states that its fixture work is included. Factory B shows a separate initial fixture charge and a lower recurring unit rate. Neither response is automatically the stronger offer.
First mark both replies against the same scope: part revision, material, critical features, pilot quantity, recurring quantity and finishing. Then create two columns for recurring and nonrecurring charges. Ask Factory A whether its unit rate remains unchanged for repeats; ask Factory B whether the fixture charge applies only once and what happens if the design changes. Record exclusions in the comparison sheet.
If you have not yet selected companies to send the request to, that is a different task covered by Ardimex’s sourcing service. This article begins once the recipients are already known.